Red Mountain

Red Mountain South LID Update
posted 10/24/2011 12:00PM

The Kennewick Irrigation District Board awarded a contract to RH2 Engineering, Inc. on October 4, 2011 for a 30 percent preliminary project design.

Project Schedule

The preliminary engineering design will be completed and presented to the Board of Directors by April 17, 2012. If the preliminary design for the project is economically feasible and acceptable from an engineering perspective to the KID Board of Directors and Red Mountain South LID water users, then the project will immediately proceed to the next phase, Final Design. [NOTE: the water users do not have a vote or a veto. They can advocate for or against the project to the Board, but the final decision is the Board’s alone to move ahead, modify or negate the LID.]

Upon KID Board of Directors’ approval of RH2 Engineering’s performance, RH2 will be awarded the final design contract for design and engineering services for the Red Mountain South LID project through a non-competitive process. If approved, the Red Mountain South LID final design project will be awarded by the KID Board of Directors in May, 2012. The final project design and engineering is tentatively scheduled for May 2012 through June 2013. The construction management phase of the Red Mountain South LID project is tentatively scheduled for June 2013 through December 2015. This project schedule is contingent upon the results of the cultural, historical, and environmental evaluation, the acquisition of rights-of-way and easements, and the Point of Diversion Change Application on the Yakima River not being appealed.

Project Cost Estimate

The cost estimate indexed from the original 2009 project estimate will be approximately $14,900,000 if construction is completed according to the current schedule.

 

LID Formation
Red Mountain South LID Approved
Resolution 2009-26 Formation of LID 192-Red Mountain South
 

Master Plan
Technical review of the Edison Street and Kiona/Red Mountain Pumping Stations

Master Site Plan

 

Maps
Red Mountain South Ownership

Red Mountain South Planning Area

 

 

Red Mountain LID Meeting Information

July 2009

July 21st Public Hearing

April 2009

April 20th Red Mountain Meeting Minutes

April 20th Consultant Presentation

April 20th Meeting - LID Progress Summary

April 20th Invitation Letter

December 2008

Dec 9th Invitation Letter

Dec 9th LID Meeting Information Sheet

Dec 9th Consultant Presentation

Dec 9th Property Owner Meeting Notes

Dec 2008 LID Summary

Meeting Materials: Red Mnt. South LID Formation

 

 

Reports

Red Mountain South LID Engineer's Report

Red Mountain South LID staff report to Board for Sept 1

Red Mountain South Planning Area Staff Report

Red Mountain LID Bond Staff Report

82 cfs Permit Allocation Staff Report

Water Re-allocation Policy Staff Report

 

 

 

If you need more information, please call the KID Customer Service Department at (509) 586-9111 or send e-mail to: info@kid.org.